An update on steam locomotive 5239 Goliath – 8th January 2019

5239 Goliath
Credit: Steve Masters

The East Somerset Railway has released an update on the overhaul work taking place on 5239 Goliath.

Work is progressing on the boiler, bunker and coupling rod bearings.

Turning to the boiler, the crown stay holes are being tapped up to the next size in preparation to take the new stays. There is 170 crown stays and specially made long taps are used.

The top hole is tapped first and then a second long tap is then used to thread the hole in the copper firebox 2 foot below.

This Sunday, the group also riveted the new firehole as well as replacing a number of wasted rivets in the front tubeplate.

Jeff has made more progress with the bunker with all the baffles fitted and the coal plate added.

Where Next?

News Homepage
   For the Latest Railway News
RailAdvent Online Shop
   Framed Prints, DVD’s / Blu-Ray’s and more
LocoStop Community
   Come and share your railway pictures
East Somerset Railway
   Visit their website

Michael Holden avatar
I have had an interest in Railways for as long as I can remember. I am a member of a number of heritage railways and actively volunteer at 2 of them. I enjoy all types of railways, real life, model and simulations. I started RailAdvent in 2014 and am the main editor of the site.