Update on steam locomotive No.82045 – August 2018

Picture of Jamie Duggan

Share:

Update on steam locomotive No.82045 – August 2018

Share:

Picture of Jamie Duggan

Share:

82045 Fitting Bush into the King Pin Hole // Credit Tony Massau
Fitting Bush into the King Pin Hole // Credit Tony Massau

August has seen work continue on the ‘bottom-end’ of the steam locomotive 82045 at the Severn Valley Railway.

Pony Trucks

Machining work on the axleboxes has continued. Once completed, the axleboxes will be sent off for specialists to carry out white metalling work.

Also, the radial arms’ kingpin holes have had their bushes fitted. Other stored parts for the pony trucks have been prepared ready for use.

Cylinders

Only one more steam chest liner has to be machined before all four are completed. The outer cladding for the cylinders is being assembled and slide bars are having their security holes drilled, refitted then reamed.

Reaming the Slide Bar Bolt Holes // Credit John Pagett
Reaming the Slide Bar Bolt Holes // Credit John Pagett

Sponsorship

Only one part for the pony trucks is left for sponsorship since the last update. This being a side check spring bar, costing £900. The Trust appreciate all the support by these items being sponsored.

Where Next?

News Homepage
   For the Latest Railway News
RailAdvent Online Shop
   Framed Prints, DVD’s / Blu-Ray’s and more
LocoStop Community
   Come and share your railway pictures
82045 Trust
   Visit their website

Responses

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Related Articles