Network Rail fixes embankment on Ipswich-Lowestoft line

Janine Booth - Contributor Add a Comment 3 Min Read
Installing piles to form strong foundations // Credit: Network Rail

has stabilised and widened a mile-long embankment on the East Line between and to the north of Martlesham.

Before the works: signage slipping down the deteriorating embankment
Before the works: signage slipping down the deteriorating embankment // Credit: Network Rail

The top of the embankment had been slipping, causing important equipment and signage to gradually fall down the bank, potentially affecting the future safe and reliable running of the line.

The stabilisation work means that worn-out track on top of the embankment can now be replaced. It also allows Network Rail to provide a footpath for railway workers on the embankment, which will give better access for maintenance.

Engineers worked over thirteen consecutive days, from Saturday 25 March to Thursday 6 April, with buses replacing trains between Ipswich and . The track replacement work will be carried out over ten consecutive days between 16-25 August, when buses will replace trains.

Using a special vacuum to uncover and move cables // Credit: Network Rail

Network Rail and have thanked passengers for their patience while the work was carried out.

Piles in place // Credit: Network Rail

Mark Walker, Network Rail Anglia route infrastructure engineer, said: “We're really sorry that passengers had their journeys disrupted over 13 consecutive days, but we needed extended access to the railway to stabilise this steep, high embankment and avoid sudden or closures. We'll be back in August to do much-needed track replacement on top of the embankment, which is also crucial to keeping trains on time. We are building an that is fit for the future.”

Dropping ballast to create the wider embankment // Credit: Network Rail

Jamie Burles, Greater Anglia managing director, said: “I'd like to thank passengers for bearing with us during this improvement work, which will help us to continue operating a punctual train service along the East Suffolk Line. Our new trains are already providing a very good service on the route and this engineering work will help ensure we can continue to deliver high standards of performance on a consistent basis and provide a more comfortable journey for passengers.”

Widened and stabilised embankment // Credit: Network Rail
Share This Article
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Exit mobile version
X