Cambrian line to close while river bridge in Machynlleth raised

Alan Holden Add a Comment 3 Min Read
Credit: Network Rail

This weekend (Saturday 15th May) work begins to raise a bridge on the Cambrian Line between and .

Black Bridge, near Machynlleth, has been flooded repeatedly in bad weather, meaning the line has to be closed until flood water subsides.

The bridge will be raised by 1 metre in a £3.6m project, which will be enough to reduce any impact from high river levels in the future.

Preparation work began in March. Now, while the main project work is carried out, the line between Machynlleth and Shrewsbury will be closed and a replacement bus service will be in operation.

Buses will be replacing trains from 15th May to 28th June, and a revised timetable will be in operation between Machynlleth, Pwllheli and Aberystwyth.

Black Bridge crosses the River Dulas in Powys. As the river is a fish spawning river, there is a limited time period when the work to raise the bridge can be carried out.

have worked with Natural Resources Wales and ecological specialists to help protect the local environment.

 

black bridge flooding
Credit: Network Rail

Kevin Giles, senior asset engineer for Network Rail Wales and Borders, said: “This is a big project for us at Network Rail and the first time a railway bridge will have been raised away from flood waters in Wales.

“The issues of flooding on this line go back more than three decades and the result is that large sections of the Cambrian line in central Wales end up cut-off and isolated while repair work is carried out.

“We want to ensure our passengers have more reliable journeys and this project highlights our dedication to making the railway more resilient in Wales.”

Alexia Course, Transport for Wales' Transport Operations Director, said: “The much-needed work will help us to provide a more reliable service during periods of bad weather and will benefit passengers using this route for many years to come.

“Our team will be working hard to support our customers throughout the improvement work. We understand disruption to services is frustrating for our customers, and we would like to thank them in advance for their patience while this work is taking place.”

Where Next?

RAILADVENT NEWS
The latest railway news
FREE NEWSLETTERS
Sign up to our daily and weekly newsletters
RAILADVENT SHOP
Prints, DVD's, Clocks, Mouse Mats and more!
COMPETITION TIME
Enter our latest competition
UK STEAM INFO
Upcoming mainline steam tours/loco movements
NETWORK RAIL
Visit their website

Share This Article
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Exit mobile version
X