Improvement work continues on the Penistone line in 2020

Michael Holden - Editor Add a Comment 2 Min Read
Credit: Network Rail

has announced that it is working with to extend the platform at station and both platforms at station in the new year.

This will mean longer trains can call at both stations.

Work starts on Saturday, 4 January to lengthen platforms 1 and 2 at Shepley station and is expected to be completed by Wednesday, 26 February.

Work to extend the platform at Honley station will begin on Monday, 6 January and is expected to be completed by Tuesday, 31 March.

None of this work will impact on train services, and Network Rail is working closely with Northern to minimise any disruption for passengers.

What did the officials say?

Matt Rice, Route Director for Network Rail, said:

“This work to extend the platforms at Shepley and Honley means passengers will benefit from modern trains with increased capacity.

“We are working closely with Northern as we extend seven stations on the line. I would like to thank people for their patience, and we will make every effort to minimise the noise whilst this work is carried out.”

Anna Weeks, Regional Director at Northern, said:

“The work being carried out by Network Rail will allow us to run better, longer trains for our customers – giving them an improved journey experience.

“We are working with Network Rail to keep disruption to a minimum and I'd like to also give my thanks to our customers for their understanding while the work takes place.”

Where Next?

News Homepage
   For the Latest Railway News
RailAdvent Online Shop
   Framed Prints, DVD's / Blu-Ray's and more
LocoStop Community
   Come and share your railway pictures
Network Rail
   Visit their website
Mainline Steam Info
   Upcoming mainline steam tours/loco movements

Share This Article
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Exit mobile version
X