Update on steam locomotive No.2968 – August 2019

Jamie Duggan - Contributor Add a Comment 2 Min Read
Axlebox Undergoing Repairs // Credit SMF

Work continues at the on overhauling sole surviving London, Midland and Scottish Railway Stanier Class 5 2-6-0 No.2968.

‘Bottom-End'

The coupled wheels have cleaned up and measured in preparation for rewheeling the frame.

The axleboxes are undergoing machining, with each one machined to match its axle.

All four coupling rods and their bushes & pins have been cleaned and are in the process of being repairs.

Coupled Wheels Cleaned // Credit SMF
Coupled Wheels Cleaned // Credit SMF

While the frame is on jacks, the team could only refit some of the various pipework and now need the frame back on its wheels before they can continue. Under the cab, the driver's side injector and related parts have been reassembled.

Boiler and Tender

Re-positioned to lay on its right-hand side, work can begin on repairing the left-hand side of the copper firebox.

Now fully reassembled, the tender's hand brake can be used now and the buffers are undergoing a repaint.

Boiler Undergoing Repairs // Credit SMF

For more information or to support the , please visit their website here.

Where Next?

News Homepage
   For the Latest Railway News
RailAdvent Online Shop
   Framed Prints, DVD's / Blu-Ray's and more
LocoStop Community
   Come and share your railway pictures

Share This Article
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Exit mobile version
X