Track replacement at Gateshead complete

Michael Holden - Editor Add a Comment 2 Min Read
Credit: Philip Barker

Nexus has announced that a programme of track modernisation at Gateshead has been completed.

is the public body which owns and manages Metro and has worked to replace 1.6km of track in the first phase of an £8m project south of the Tyne.

The work forms part of the £350m Metro all change modernisation programme.

Track beds, sleepers, and rails were replaced on a section of line between Gateshead Stadium and Felling Metro stations over three-weekend line closures.

A total of 2,300 new railway sleepers have been installed and 8,000 tonnes of new track ballast.

What did the officials say?

Acting Director of Rail and Infrastructure at Nexus, Michael Ellison, said:

“This was vital modernisation work to ensure that a key section of line in Gateshead can carry Metro trains for many years to come.“We're investing £8m in new Metro tracks south of the Tyne and I'm grateful to our customers for their patience while the work was carried out.

“We packed a huge amount of work into three weekends to replace a total of 1.6 kilometres of Metro line. Working at weekends ensures that we can keep lines open on Metro's busiest days between Monday and Friday.”

Where Next?

News Homepage
   For the Latest Railway News
RailAdvent Online Shop
   Framed Prints, DVD's / Blu-Ray's and more
LocoStop Community
   Come and share your railway pictures
Nexus
   Visit their website

TAGGED:
Share This Article
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Exit mobile version
X