The ‘Raise the Roof’ appeal launched earlier this year by the Severn Valley Railway has reached nearly half a million pounds, and the first contract for the work has been signed.
The appeal, which brought in a quarter of a million pounds after just two months, will fund the building of a canopy at Kidderminster Town station, the southern terminus of the West Midlands heritage railway. The work will be carried out by Walsh Construction, which is based in Worcester.

Part of the canopy will be constructed using steelwork salvaged from the former Great Western Railway station at Wolverhampton Low Level, giving it authenticity and making a contribution to railway preservation.
Construction will start in January next year, with Walsh Construction installing the drainage and foundations, resurfacing the platform and erecting the steel framework during the Railway’s winter closure.
The Railway will be able to operate smoothly when it reopens for events during the February half-term break.
The second phase of building will be carried out in November 2027, when the roof cladding will be installed. Construction will then take a festive break before the third and final phase starts in January 2028, completing the fascia boarding and finishing touches.

The Raise the Roof fund now stands at just under half a million pounds, boosted by the addition of remaining funds from a significant legacy. This is a fantastic milestone and testament to the generosity of our supporters.
With the construction contract signed and steelwork ordered, this long-held ambition is becoming reality. But there is still work to do, and we are redoubling our fundraising efforts to secure the funds needed to complete the full project.
We’re hugely grateful for the support so far and urge everyone who cares about the future of the SVR and railway heritage to help us maintain this momentum.
Judith Meredith, Chair of the Severn Valley Railway Charitable Trust