The Office of Rail and Road has rejected plans from multiple operators for new services out of London Euston, citing capacity issues as the reasons behind their decision.
The ORR says that an assessment found that adding more trains would increase delays and cancelled trains.
The rejected services are Wrexham, Shropshire and Midlands Railway’s plans for four return Wrexham – London Euston services, Lumo’s plan for four return Rochdale – London Euston services, and Avanti West Coast’s plans for additional Blackpool North – London Euston services.
An external review has found that the southern section of the West Coast Main Line has not had any capacity boosts and gaps in the timetable need to provide space for trains to recover when disruption occurs.

The ORR has approved a new service from Chester, the 19:29 to London Euston. This train runs as a fully crewed empty service, so the ORR says this does not add another train to the route.
This will be disappointing to the various TOCs, especially WSMR, who ran a special charter service earlier this year to showcase how a service would run. You can see a video of this below:
“New services, destinations and greater choice can bring real benefits for passengers and communities. But the West Coast Main Line is already under significant pressure, with performance reflecting limited resilience on a heavily used part of the rail network.
Stephanie Tobyn, ORR’s director of strategy, policy and reform“Our detailed analysis has shown that adding more trains to the current timetable would reduce the ability to recover when disruption occurs, increasing the risk of delays spreading and making reliability of the network worse for all passengers.”



Responses
“This [additional] train runs as a fully crewed empty service, so the ORR says this does not add another train to the route.”
I hope that the full text of the ORR report explains this contradiction! Maybe, for instance, no-one cares if it runs late. It would be nice to have confidence in their lack of logic