Manchester Airport trains to be cancelled this December

Picture of Roger Smith

Share:

Manchester Airport trains to be cancelled this December

Share:

Picture of Roger Smith

Share:

A TransPennine Express Class 185 arrives into Manchester Airport
A TransPennine Express Class 185 arrives into Manchester Airport // Credit: Josh Haworth

Train services in and out of Manchester Airport railway station will be suspended for one day on Sunday, 6th December because of engineering works.

The work is part of a £115 million investment in the station to provide additional capacity and more flexibility in operating train services.

Further closures will take place through to the middle of 2028.

A Class 397 at Manchester International Airport Station
A Class 397 at Manchester Airport Station // Credit: TransPennine Express

During the closure, rail replacement buses will operate between Wilmslow and Manchester Airport, and customer-handling teams will be on hand to provide information to passengers.

Metrolink services will be unaffected.

Included in the work being carried out is:

  • Extending Platforms 1, 2 and 3 to create extra capacity so that two six-car trains can use the platforms simultaneously.
  • Upgrading the track layouts on the approach to the station to improve operational flexibility.
  • Upgrading and modernising the signalling systems.

Taking advantage of the station’s closure on Sunday, 6th December, engineers will build a utility bridge across the railway to accommodate electrical cables.

That will enable another bridge structure at the airport to be removed next Easter 2027, and be replaced by a new one later next year.

The work at Manchester Airport railway station is part of the wider Manchester Rail Upgrade, which includes:

Further information about the work can be found here.

“We’d like to thank our customers in advance for their patience while this major investment is delivered at Manchester Airport station. The £115 million upgrade will bring long-term benefits for everyone who travels through the station, creating more capacity, improving reliability and supporting more frequent services in the future. “We are working closely with Network Rail and our industry partners to minimise disruption during the work and would encourage customers to check their journey before travelling while these essential upgrades are taking place.”

Chris Nutton, Director, TransPennine Express Major projects & Transpennine Rail Upgrade