Engineers have completed the construction of the central section of the 1-mile-long cut-and-cover ‘green’ tunnel for HS2 at Wendover in Buckinghamshire.

Work will now focus on the portals, internal works, and backfilling, and the realignment of Ellesborough Road, which crosses the tunnel.

The last segment of the Wendover green tunnel being lifted into position. // Credit: HS2
The last segment of the Wendover green tunnel being lifted into position. // Credit: HS2

By using a cut-and-cover principle for the tunnel, the noise and disturbance from the railway for people living nearby will be minimised.

The tunnel is being built inside a cutting alongside the A413 west of Wendover, and as each section is completed, earth is being replaced on top of the tunnel so that it blends into the surrounding countryside.

HS2 has four other green tunnels, with the Copthall tunnel on the outskirts of London being completed this summer, and the last roof segment of the Burton Green tunnel in the West Midlands was installed in July.

The Wendover tunnel has an ‘M’ shape, and is being assembled from 2,740 pre-cast concrete segments, with separate halves for northbound and southbound trains.

To speed up construction, the tunnel is being built in two sections. This allows excavation, preparatory work, construction, and backfilling to be carried out at different points simultaneously. The two sections met this week, and the last segment was installed on Monday, 5th October.

To construct a level base for the tunnel required the excavation of more than 1.2 million cubic metres of material, mainly chalk, and storage on site. That is now being reused to backfill the tunnel, where it will be compressed so that there is an even distribution of weight across the structure.

To construct a level base for the tunnel required the excavation of more than 1.2 million cubic metres of material, mainly chalk, and storage on site. That is now being reused to backfill the tunnel, where it will be compressed so that there is an even distribution of weight across the structure.

Umesh Gorasia, HS2 Ltd’s Project Manager, commented that it is great to see the two halves of the tunnel linked up for the first time. Once complete, the green tunnel will dramatically reduce disruption from passing trains and blend the railway into the countryside.

Aerial view of the last segment of the Wendover green tunnel being lifted into position. // Credit: HS2
Aerial view of the last segment being lifted into position. // Credit: HS2

“EKFB installed the first concrete segment in spring 2025, and in less than 18 months, we have lifted more than 2,000 segments to complete the central structure of the Wendover green tunnel. This was a huge undertaking and has required the expertise of a skilled workforce. The team has worked together to safely overcome challenges, keeping productivity high and pushing the construction programme forward. “Seeing the two halves of the tunnel finally come together was a proud moment for everyone involved.”

Elton Qafaliaj, Project Manager for EKFB, HS2’s main works contractor responsible for the central section of the route through Buckinghamshire and into South Warwickshire