HS2 completes 320m-long Northamptonshire viaduct

Picture of Janine Booth

Share:

HS2 completes 320m-long Northamptonshire viaduct

Share:

Picture of Janine Booth

Share:

View of the completed Westbury viaduct crossing the floodplain of the River Great Ouse, October 2026
View of the completed Westbury viaduct crossing the floodplain of the River Great Ouse, October 2026 // Credit: HS2

HS2 engineers have completed the construction of a major viaduct that crosses a floodplain of the River Great Ouse near Brackley.

The Westbury viaduct is 320 metres long and is set low in the landscape to the east of Brackley.

Engineers built it using a ‘double composite’ approach, using less carbon-intensive concrete and steel than a traditional design.

The construction method, which took inspiration from the recent building of viaducts on the French TGV network, uses a layer of reinforced concrete above and below the steel beam, which creates a box beam.

The steel beams weigh 2,695 tonnes and were assembled on the north abutment. Workers then slid them into place using pads covered in a non-stick coating similar to the surface of a frying pan. This minimised friction between the deck and the temporary steel bearings on top of the concrete piers.

This stage of the work was completed in October 2024.

View of the Westbury viaduct from the wildflower meadow beneath the structure during the final stages of construction Spring 2026
View of the Westbury viaduct from the wildflower meadow beneath the structure during the final stages of construction, Spring 2026 // Credit: HS2

The next stage of construction was to use a travelling formwork to cast the concrete deck. Engineers did this in 42-metre-long sections, pulling the formwork forward each time to allow the next section to be cast. Then, the prefabricated parapets along the edges were lifted into position.

The Westbury viaduct is the longest viaduct in the Brackley area. It is one of fifteen viaducts that contractor EKFB is building for the central section of the HS2 project.

Now that the construction is completed, engineers will remove the hardstanding surface beneath the viaduct and will finish the landscaping work.

Close-up of the weathering steel beam and concrete parapets of the Westbury viaduct, October 2026
Close-up of the weathering steel beam and concrete parapets of the Westbury viaduct, October 2026 // Credit: HS2

HS2 is continuing construction work on other viaducts, including the Saltley viaduct in Birmingham.

It’s fantastic to see Westbury Viaduct structurally complete.

This viaduct showcases the innovation, technical expertise and collaboration behind the build. Its double composite design has created a lighter, more efficient structure that uses less concrete. As the first of five viaducts to be completed, that are designed and built in this way, this milestone demonstrates EKFB’s ability to deliver complex engineering solutions with both sustainability and design in mind.

Thank you to everyone involved in delivering this structure safely. This achievement would not have been possible without the expertise of our supply chain partners, including Eiffage Metal, who led the manufacture and installation of the beams, and Infrasolutions Ltd., whose specialist deck finishing works were key to bringing the structure to completion.

EKFB Project Sub Agent, Arman Yarali