Derbyshire railway line to close for nine days

Picture of Janine Booth

Share:

Derbyshire railway line to close for nine days

Share:

Picture of Janine Booth

Share:

Matlock Bath
Matlock Bath // Credit: Network Rail

The Derwent Valley line in Derbyshire is set to close for nine consecutive days in November while Network Rail carries out improvement work.

No passenger trains will run on the line between Saturday 14 and Sunday 22 November (inclusive), while workers renew more than 4.5 miles of track between Matlock and Derby. It is expected to reopen on Monday 23 November.

The track will be renewed at three different sites along the line – Matlock Bath, Cromford and near Whatstandwell station.

As well as renewing the rails, workers will also renew 3,509 sleepers and 6,400 tonnes of ballast. 

Whatsandwell station
Whatsandwell station // Credit: Network Rail

Network Rail’s workers will be using eight engineering trains. Among these will be a New Track Construction train, which lays new rails and sleepers.

This means that the renewal work can be carried out more quickly and at a lower cost.

These trains have also been used in other track-laying work, including between Oxford and Blatchley on the East West line and in the construction of high-speed railway HS2.

Replacement buses will be provided, calling at all stations. However, Network Rail is cautioning passengers that the bus stops may be a short distance from the station.

Network Rail is also reassuring passengers that train services between Derby and Sheffield via Chesterfield will not be affected by the work.

Cromford station
Cromford station // Credit: Network Rail

We’d like to thank our customers for their patience and understanding while this vital work takes place. We understand that changes to your journey can be disruptive, and we appreciate your support while we work to improve our railway.

Customers can find details of rail replacement bus stop locations on our station webpages. As some stops may be a short distance from the station, we encourage anyone who needs extra support or is unable to use the walking route to get in touch with our dedicated Passenger Assist team, who will be happy to help.

Clear signage will be in place to help customers find their way, but we recommend allowing a little extra time for your journey to help you travel as smoothly as possible.

Philippa Cresswell, customer experience director at East Midlands Railway