Work on Manchester Victoria’s staircases has begun, with the installation of new flights of stairs included as part of the upgrade works across the confines of the station.
As part of the Manchester Rail Upgrade (which includes the now-completed Wigan to Bolton electrification scheme), the project aims to boost rail capacity across the North West.
The work at Manchester Victoria will be undertaken by Story Contracting and will last until spring next year.
With over 8.3 million passengers using Manchester Victoria each year, the stairwells see a lot of use on a day-to-day basis.
The steps leading from the station’s footbridge to the platforms are all on one side, which leads to them becoming extremely busy at peak times, especially after a train arrives.

The new stairways will be added on the opposite sides of the current stairways down to platforms 4, 5 and 6.
These will add more capacity, greatly ease congestion on the existing stairways and allow passengers to clear the platforms more quickly.
During the works, the lifts will still be available for use, though platforms 4, 5 and 6 will be temporarily reduced to allow the new stairways to be built.

“The stair and footbridge improvements at Manchester Victoria station are part of a wider investment across the North West to improve and increase train services in the coming years. When complete it will immediately improve how passengers move between the main concourse and platforms. In the longer-term it’ll mean more trains can serve the station in future.
“We’ve carefully planned our work around events at Manchester AO Arena during the project and are working closely with all train operators while it takes place. I’d like to thank people in advance for their patience while we complete these important upgrades.”
Nicky Gill, Network Rail sponsor,
“We’re proud to be playing our part in improving Manchester Victoria Station for the millions of people who use it each year.”
“Delivering major improvements in a live station environment requires careful planning and close collaboration between all project partners. Our focus will be on delivering the work safely and efficiently, while keeping disruption to passengers and day-to-day station operations to a minimum throughout the project.”
Dan Smithson, Story Contracting head of operations,



Responses
Unfortunately the short sighted thinking in tge late 1980s and early 90s allowed tge reduction from 17 platforms to just 6, the adjacent Arena has made any capacity improvements impossible without demolishing the Arena. As for the original subway i would love to know what happened to it during the rebuilding in 1992/3. There still seems little prospect of any improvement on the Castlefield Corridor pinch point so basically Manchester is permanently stuck now with a badly designed rail system between Piccadilly, Oxford Road and Victoria
John’s point about the old subway is fascinating. There would have been no reason to fill it in so it must be down there somewhere. Anyone on here from Network Rail?
However, I knew the old Victoria in the 70’s and I was there again last week for an event at the Arena seeing folk arriving by trains from all directions!
A bright modern interchange for train and metro .. with a roof that doesn’t leak. The old original L&Y features still there.. and old photographs on display. It’s far from vandalised.
I even came in via the Ordsal link because there was a connecting train. The odds were against that it must be said … but it’s the lack of capacity between Picc and Deansgate that’s the real and now unsolvable capacity problem.
While this is very welcome, it is extra platforms that are needed, so that Ordsal link would not be the huge ‘white elephant’ it has become.
When the truly awful Arena was built for the failed Olympic Bid, a far better subway was buried (it may well still exist). This would have relieved the passenger traffic if it were to be reinstated.
Lancashire & Yorkshire Railway were a truly remarkable and forward thinking company. Man Vic was easily the best of Manchester’s stations, and the vandalism wrought on it by alleged railway managers is a total disgrace.