M42 reopened after weekend HS2 work

Picture of Roger Smith

Share:

M42 reopened after weekend HS2 work

Share:

Picture of Roger Smith

Share:

The final Water Orton span being lifted across the M42.
The final Water Orton span being lifted across the M42.. // Credit: HS2

Installation of the last of six spans of the Water Orton viaduct in the West Midlands, over which HS2 will cross the M42, was completed early yesterday morning, Monday, 21st September.

Lifting the spans required closing the M42, and the motorway reopened at around 4 am as scheduled. During the closure, engineers were also lifting the last beams of another HS2 bridge. That one is known as the ‘twin box’, and is a 300-metre-long structure near the NEC formed of two boxes.

Deck beams being lifted at the M42 twin box site
Deck beams being lifted at the M42 twin box site // Credit: HS2

Whilst the M42 was closed, National Highways took the opportunity to demolish the Bickenhill Bridge on the northern side of the roundabout at M42 junction 6. Work will now continue to install the remaining parapets of the Water Orton viaduct, and prepare the twin box ready to lay railway lines.

There are two viaducts at Water Orton, and they cross the M42, A446, the Birmingham to Peterborough railway line, and the River Tame. They are at the apex of a triangular ‘delta junction’ linking Birmingham with the mainline heading north. The final spans of the first viaduct at Water Orton were installed in August. The second Water Orton viaduct still needs to be extended by another 40 metres to close the final gap above Gilson Road, and that will be completed in the coming days.

The M42 will be closed again from 9 pm on Friday, 23rd October to 5 am on Monday, 26th October, to allow engineers to install parapets on the sections of the viaduct immediately above the motorway. During the same weekend, engineers will also carry out the fourth and final slide of the west deck of the M6 South Viaduct. These works will not affect the M6 motorway, which will remain open, as only the connector road from the M42 North to M6 North will be closed.

CGI showing how the HS2 line will cross the M42 twin box
CGI showing how the HS2 line will cross the M42 twin box. // Credit: HS2

“The twin box and Water Orton Viaducts are three major structures that cross the busy M42 motorway. In just four weekends, we’ve completed the bridging works on each of them, closing the gap over the north and southbound carriageways. This was a huge engineering challenge, and I’m so proud of the way our teams have responded. Their skill, dedication and hard work throughout the summer means we can move forward to the next exciting phase of our work.”

Oliver Shore, Project Director, Balfour Beatty VINCI