Over the last 28 days, engineers have been working on Transpennine Route Upgrades (TRU) in West Yorkshire.
From the 30th May until the 27th June, improvements were made between Morley and Dewsbury.
A range of track renewals, drainage works, overhead line equipment installs, station and bridge works, were carried out.
Both Dewsbury and Batley were the focus of the station improvement works, which drew them both closer to completion.
Weekend work will continue over July and August, ahead of the 16-day planned improvement works.
Services will be disrupted:
- 4-5 July
- 11-12 July
- 18-19 July
- 25-26 July
- 1-2 August
Customers should plan ahead and check online before travelling.
You can read more about TRU here.
“We’re delighted to have completed this latest series of work safely and on time, thanks to the hard work of our teams and the support of our customers and our communities. TRU has made great strides in delivering a more reliable, electrified railway across the Pennines so far this year, with significant station upgrades delivered, too.
“By the end of summer, we look forward to unveiling a transformed Batley station with a brand-new footbridge, lifts and platforms, which will greatly improve step-free access around the station. At Dewsbury, we will be introducing better waiting facilities and extended platforms.”
“I’d like to say a big thank you to our teams who worked around the clock and throughout the recent very hot weather.”
Jonathan Hepton, project sponsor for TRU