A six-day closure is planned for a busy section of the Metro line to allow for track work to take place.
From the 26th of October until the 31st of October, the work will take place between Benton and Wallsend, with the route reopening on the 1st of November.
They will be renewing a track junction at Monkseaton, and 600 metres of new track will be installed, resulting in a total of 2,700 tonnes of ballast and 900 sleepers being put in place.
This renewal work is part of the Metro Asset Renewal Programme, which aims to modernise parts of the Metro infrastructure.
During the closure, they will also carry out other maintenance, landscape management and station repairs at Whitley Bay and Tynemouth.
Replacement buses will be in place to keep people moving. The number 900 will operate from Four Lane Ends Interchange to Wallsend and will stop near or at all Metro stations.
Customers are advised to plan ahead and allow extra time to arrive at their destinations.
“We’re investing in new track to ensure to ensure Metro continues to reliably serve North Tyneside for many years to come.
“The track junction at Monkseaton is vital. It carries hundreds of Metro services and is now in need of a complete renewal. This work can only be carried out safely during a six-day closure of the Metro system between Benton and Wallsend.
“To make the most of the closure, we are also carrying out a range of other works at the same time, including landscape management, track maintenance, and station repair work at Tynemouth and Whitley Bay.
“There is no good time to close a section of line, but our plans consider school holidays, to ensure the least possible disruption to customers and the most efficient works. This project ensures that a vital section of the Metro system is future proofed and reliable for the long term.
“A frequent replacement bus service will run in the affected area so that customers can still travel around on public transport. The buses will get everyone where they need to be during the closure.”
Paul Welford, Major Projects Director at Nexus