Transport for Wales (TfW) reports that its intensive eight-month programme to transform and electrify the Rhymney Valley railway line is making significant progress.
Next Saturday, 19th July, will be the start of a second six-week railway line closure between Caerphilly and Rhymney with no train services until Sunday, 31st August.
Construction work on the upper Rhymney Line started in March, since when over 15 kilometres of railway track have been upgraded. In June, the last of 693 foundations that will support the Overhead Line Equipment (OLE) to power the new electric trains between Caerphilly and Rhymney was completed.
So far, 466 steel support posts, or 55% of the overall total, for the overhead wires have been installed.
Ground investigations on the line began in late 2024. Initially, 50% of the foundations had problems with their piling, which could have led to costly return visits and more disruptions for residents, so in April, the line was closed for six weeks to give the installation teams more access to the line, allowing them to work more efficiently.
Increased access to the line through extended closures allowed teams to conduct foundation probing to check the level of bedrock, which allowed the approach or design for the Overhead Line Equipment (OLE) system to be changed. Adjusting piling methods to suit the bedrock conditions has resulted in the refusal rate dropping from 50% to just 0.3%.
Extended line closures have also allowed most of the noisy piling work to take place during the daytime, significantly reducing the impact on nearby residents.
During the closure of the Upper Rhymney Line between Caerphilly and Rhymney from Saturday, 19th July to Sunday, 31st August, rail replacement bus services will be provided. However, the line will be reopened for fans visiting the Catfish And The Bottlemen concert at the Principality Stadium on Friday, 1st August.
Further information about closures of the Rhymney Line, rail replacement bus services, and the location of local bus stops is available on the Rhymney Line website.
The upgrades being carried out now will enable the introduction of brand-new tri-mode Class 756 trains, which provide faster, greener, and more accessible transport for the area’s communities.



Responses
Shame that the Cardiff Central-Swansea section isn’t electrified since the South Wales main line electrification has reached Cardiff Central.